Generating control data

To generate the control data:

  1. Access the Generate Control Data (tpptc1230m000) session.
  2. Select a single or range of projects. You can click Details to select the projects based on project status, project contracts, project classification and so on.
  3. Select the Net Change Run check box only if you want to generate the budget changes in the control data.
    Note: 
    • If this check is selected, the time required to generate the control data is reduced. If this check box is cleared, Infor LN does a complete run of the process.
    • A net change run can cause zero lines in the control data (report). The control data report can have zero lines if the project budget is based on Element and the control budget is based on Activity, and you replace an activity on an element budget line.
    • The zero line is displayed to show the changes to the activity budget in the control data.