Cancel Production Schedule Lines (tirpt4202m300)
Use this session to cancel Production Schedule Lines with the status Released.
Note:
- You can access this session only if the Repetitive Manufacturing (RPT) check box is selected in the Implemented Software Components (tccom0100s000) session.
- You can use the
- Work Cell Planning (tirpt4102m200)
- Production Schedule Lines (tirpt4102m000)
option from these sessions to access this sessions: - You can cancel the lines in the Production Schedule Lines (tirpt4102m000)session only if:
- The Production Schedule Line status is Released.
- The status of the line linked to the order in the Production Warehouse Orders (timfc0101m000) session is open or does not exist.
- The status of the line linked to the order in the Production Warehouse Orders (timfc0101m000) session is Planned in case of Backflush.
- The Tool Requirement Status is Unallocated or Not Applicable.
- The locked production schedule lines in the Production Schedule Lines (tirpt4102m000) session can be canceled if the line status is set to Released.
- The production schedule lines in the Production Schedule Lines (tirpt4102m000) session can be archived and/or deleted using the Archive/Delete Production Schedules (tirpt4201m100) session only if the status of the lines is set to Canceled.
Field Information
- Selection Range
-
- Site
- The code of the site linked to the
selected company.Note:
- This field is displayed only if the Sites field is Active in the Implemented Software Components (tccom0100s000) session.
- You must specify a value in this field to lock production schedule lines.
- The application defaults this value from the Production User Profiles (timfc0120m000) session, if the site is specified for the currently logged in user.
- This field is enabled only if the All Sites allowed check box is selected in the Production User Profiles (timfc0120m000) session.
- Work Cell
- The code of the work cell.Note:
- The work cell field is mandatory to select and cancel production schedule lines.
- The linked schedule line materials are automatically deleted from the Schedule Line Materials (tirpt4121m000) session after canceling the production schedule lines.
- Production Schedule
- The From and To fields define a range of production schedules.
- Lines
- The From and To fields define a range of
production schedule lines with status Released.Note:
- You can select the option from the menu to display all production schedule lines including canceled ones.
- Production Schedule Lines with the status Active are included in the skipped records because Production has already started.
- You can check the unsuccessful cancellation warning message using LN UI MessageViewer.