Standard Routing

A standard routing is a routing that can apply to multiple items. By using the Item - Routings (tirou1101m000) session, you can predefine a routing code.

Note: Only applicable if theJob Shop by Site parameter in the Concept Activation (tcemm4600m000) session must be set to Active or In Preparation.
  1. Start the Items - Production by Site (tiipd0151m000)
  2. Select the item for which you want to manage the routings.
  3. Select the site for which you are creating a routing. Note: You must be authorised to manage the site for which you are creating a routing.
  4. In the References menu use the Routings command to start the Item - Routings (tirou1101m000) session. This will allow you to manage routings for the selected item.
  5. Specify the required routing code and its description in the Routing field. The Standard field is now Yes.
Manufactured item
Routing 111
Standard Routing Yes

Later on, you can link the standard routing to one or multiple items in the Item - Routings (tirou1101m000) session by selecting a manufactured item and site when you record a new item routing code. First, select the Standard checkbox in the Item - Routings (tirou1101m000) details session. Next, select a standard routing to which the new routing can be linked. The operation data is adopted from the standard routing during the input of a production order.

Manufactured item: bicycle saddle
Routing 222
Standard Routing Yes, 101
item routing standard routing
Note: If the Standard check box is cleared, the routing is not linked to the standard routing. As a result, you must manually enter a routing.