Example 1: Activity has not yet started

Activity A has not yet started. No hours have been spent, there is no project structure, and there is no detailed capacity planning.

  • Activity duration (project days): 15
  • Rough capacity requirement : 200
  • Earliest start date : day 4 week 44 year 92
  • Percentage completed : 0%

The current date lies before the earliest start date. The following figure depicts activity A being carried out:

WWorkdays
_Non-workdays

The capacity load table assigned to the activity is shown in the following figure:

The capacity for activity A is 200 hours. The capacity load per week is as follows:

Week Number of days Percentage of Activity Duration Percentage of Capacity Requirement Difference Compared to Prev. Wk. Capacity Requirement (per Week)
44-92 2 13% 17.3% 17.3% 34.6
45-92 6 40% 40.0% 22.7% 45.4
46-92 9 60% 40.0% 0.0% 0.0
47-92 12 80% 70.0% 30.0% 60.0
48-92 12 80% 70.0% 0.0% 0.0
49-92 15 100% 100.0% 30.0% 60.0