Reporting operations as completed

When all items are processed in an operation, you can report the operation as complete. This is not mandatory, unless the operation is a count point.

You can do this in the Report Operations Completed (tisfc0130m000) session.

If you report an operation completed, the operation status changes to Completed. If necessary, you can reset the operation status to Started.

Quality management

In certain situations you cannot report an operation completed before the inspection order for the operation has been processed. This is explained in the Using QM for manufacturing operations topic.

Blocked operations

If an operation is blocked, you cannot report it completed.

Quantities completed and rejected

You must specify which quantity of the item has been completed successfully and how much must be rejected for not meeting the required quality. For more information, refer to Reporting quantities as completed and rejected.

If you want to report an operation completed, while the reported quantities do not match the quantities reported in the previous operation, the previous operation can be updated automatically. This depends on the Reporting Method for Previous Operations field in the Production Order Parameters (tisfc0100s000) session.

If an operation has been reported completed, all previous operations must have been completed.

You can also report all previous operations completed in the same way. However, a count point operation cannot be reported automatically via a follow-up operation. Report these operations individually.

If you report items as rejected, LN sometimes requires you to enter a reason for the rejection.

JSC Order groups

You can report the operations for all the production orders in an JSC order group completed in the Report Operations Complete by Order Group (tisfc0205m000) session.