RFQ Criteria by Criteria Set (tdpur1192m000)

Use this session to link RFQ criteria to an RFQ criteria set.

In this session, you must also assign weightings to the various RFQ criteria.

Field Information

Criteria Set

RFQ criteria set

Criterion Type

The type of criterion linked to the RFQ criteria set.

Allowed values

Obsolete

The score is based on the net purchase price. The lowest price gets the highest score.

Obsolete

The score is based on the difference between the requested quantity and the offered quantity. The exact values and scores can be specified in the RFQ Criterion Scoring Schemes (tdpur1193m000) session.

Obsolete

The score is based on the difference between the requested delivery date and the offered delivery date. The exact values and scores can be specified in the RFQ Criterion Scoring Schemes (tdpur1193m000) session.

Obsolete

The score is based on vendor rating.

Subjective

The score is based on subjective criteria. The exact values and scores can be specified in the RFQ Criterion Scoring Schemes (tdpur1193m000) session.

Obsolete

The score is based on the price including bidder landed costs, excluding third party landed costs. The lowest price gets the highest score.

Obsolete

The score is based on the net price, which includes all landed costs (bidder and third party). The lowest price gets the highest score.

Note: You can link more than one subjective criterion to a criteria set.

Criterion

The code of the criterion.

Note: 
  • If the Criterion Type is set to Subjective, you must specify a criterion that is defined in the RFQ Subjective Criteria (tdpur1191m000) session.
  • If the Criterion Type is set to Objective, you must specify a criterion that is defined in the RFQ Objective Criteria (tdpur1194m000) session.
  • The combination of the Criteria Set, Criterion Type and the Criterion must be unique.
Weighting

Because in a criteria set, not all criteria are equally important, specify the weighting of each criterion in the criteria set. The weightings are taken into account when calculating the scores for the bidders.

The weighting is relative, so the sum of all weightings of a criteria set need not be equal to 100.