RFQ Negotiations (tdpur1109m000)

Use this session to specify a bidder's response (bid), or a negotiator's counter proposal to the bid.

This session is used as a tab in the RFQ Negotiations (tdpur1606m000) session.

Note: 

After a bid or counter proposal is specified, the Acknowledged check box must be selected for the negotiation line.

Next, the negotiation process can be:

  • Continued, by specifying another counter proposal or bid
  • Finished, by changing the response line's status from Negotiating to Accepted or Rejected in the RFQ Responses (tdpur1506m000) session

Field Information

RFQ

request for quotation (RFQ)

Status

The status of the RFQ response line.

Allowed values

Created

The RFQ object is created.

Sent

The RFQ object includes one or more linked bidders and is printed in the Print Requests for Quotation (tdpur1401m000) session.

Modified

The RFQ object is changed after it is printed.

Responded

An RFQ response line automatically receives this status when a response line with the Sent status is manually updated in the RFQ Responses (tdpur1506m000) session. You can also manually specify this status in the RFQ Responses (tdpur1506m000) session.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

In Process

At least one response line is updated in the RFQ Responses (tdpur1506m000) session, which means the response has the Responded, No Bid, No Response, Negotiating, Accepted, or Rejected status.

This status is only applicable for RFQ headers, lines, and bidders. An RFQ response line cannot have this status.

No Bid

No response line will be received from the bidder to the RFQ (line). You must manually specify this status in the RFQ Responses (tdpur1506m000) session. You cannot update response lines with this status.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

No Response

No RFQ response line is received from the bidder to the RFQ (line). You must manually specify this status in the RFQ Responses (tdpur1506m000) session. You cannot update response lines with this status.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

Negotiating

The negotiator is negotiating with the bidder about the response line. A response line automatically receives this status when a negotiation record is specified for the response line in the RFQ Negotiations (tdpur1606m000) session.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

Accepted

The response line that is received from the bidder for the RFQ (line), is accepted. You must manually specify this status in the RFQ Responses (tdpur1506m000) session. You cannot update RFQ response lines with this status.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

Rejected

The response line that is received from the bidder for the RFQ (line), is rejected. You must manually specify this status in the RFQ Responses (tdpur1506m000) session. You cannot update RFQ response lines with this status.

This status is only applicable for RFQ response lines. RFQ headers, lines, and bidders cannot have this status.

Processed

The RFQ object is converted in the Convert RFQs (tdpur1202m000) session, or a response line with the Conversion Action specified as Ignore, is processed in the Process Non-Converted RFQ Responses (tdpur1223m000) session.

Line

response line

Sequence

The request for quotation (RFQ) line's sequence number, which is greater than one if it includes an item that can be an alternative for the preferred item.

You must manually specify alternatives in the RFQ Lines (tdpur1502m000) session.

Example

The sequence numbers defined in the current field, represent the RFQ lines in the most suitable alternative sequence. So, sequence number one represents the first preferable item that can be an alternative for the originally preferred item, sequence number two represents the second item that can be an alternative, and so on.

Bidder

buy-from business partner

Item

item

Line

The number of the negotiation line that is linked to the response line.

Acknowledged

If this check box is selected, the bid or counter proposal is acknowledged for the negotiation line.

Note: 

To select this check box, on the appropriate menu, click Acknowledge.

A new negotiation line can be specified only when all other negotiation lines are acknowledged for the response line.

Acknowledgement Date

The date on which the bid or counter proposal was acknowledged for the negotiation line.

Negotiator

The person who performs the negotiations for the negotiation line.

Counter Proposal Response Date

The date on which a response is expected on the negotiator's counter proposal.

Date

The date on which the bid was specified.

Default value

Current date.

Counter Proposal Date

The date on which the counter proposal was specified.

Default value

Current date.

Planned Receipt Date

The date on which the items are scheduled to be delivered on the response.

Default value

The Planned Receipt Date from the RFQ Responses (tdpur1506m000) session.

Expiry Date

The date on which the bidder's bid expires.

Counter Proposal Receipt Date

The date on which the items are scheduled to be delivered on the counter proposal.

Receipt Period Start Date

The start date of the period that the items are scheduled to be delivered on the response.

Default value

The Receipt Period Start Date from the RFQ Responses (tdpur1506m000) session.

Counter Proposal Receipt Period Start Date

The start date of the period that the items are scheduled to be delivered on the counter proposal.

Receipt Period End Date

The end date of the period that the items are scheduled to be delivered on the response.

Default value

The Receipt Period End Date from the RFQ Responses (tdpur1506m000) session.

Counter Proposal Receipt Period End Date

The end date of the period that the items are scheduled to be delivered on the counter proposal.

Lead Time

The order lead time on the response.

Lead Time Unit

The unit in which the lead time is expressed.

Counter Proposal Lead Time

The order lead time on the counter proposal.

Counter Proposal Lead Time Unit

The unit in which the lead time is expressed.

Price

The price per item unit that is offered by the bidder. The price is expressed in the bidder's currency.

Price change

The price is updated automatically when the Item and Quantity fields are changed.

Note: If the Material Pricing in Procurement check box is selected in the Material Price Parameters (tcmpr0100m000) session, this price can include material base prices.

Material Price

The response's total material price.

Currency

The currency unit in which the item's price is expressed.

Default value

The default value is the purchase price unit recorded in the Items - Purchase (tdipu0101m000) session.

You can purchase items in a unit other than the one in which their inventory is registered. Therefore, the price can be stated in different units. Goods can, for example, be stored in grams and purchased in kilograms, but priced in boxes.

Note: You must first define the currency units in the Units (tcmcs0101m000) session. In this session, you can define the conversion factor for conversion of the unit to the basic unit. If you want to use a purchase price unit that is not the same as the basic unit, this unit must first be defined in the Conversion Factors (tcibd0103m000) session. In the Conversion Factors (tcibd0103m000) session, the conversion factor from the alternative (purchase price) unit to the inventory unit is also recorded. You cannot use this method for cost items or service items. For such items, all units can be used, as they are not kept in stock.
Price Unit

purchase price unit

Counter Proposal Price

The price per item unit that is counter offered by the negotiator.

Note: If the Material Pricing in Procurement check box is selected in the Material Price Parameters (tcmpr0100m000) session, this price includes material prices.

Counter Proposal Price Unit

purchase price unit

Counter Proposal Material Price

The counter proposal's total material price.

Price Book

The price book on the response.

Counter Proposal Price Book

The price book on the counter proposal.

Price Stage

The price stage on the response.

Counter Proposal Price Stage

The price stage on the counter proposal.

Response Multi Level Discount

If this check box is selected, a multilevel discount is applied to the response.

Counter Proposal Multi Level Discount

If this check box is selected, a multilevel discount is applied to the counter proposal.

Discount %

The discount percentage on the response.

Counter Proposal Discount Percentage

The discount percentage on the counter proposal.

Discount Amount

The discount amount on the response.

Counter Proposal Discount Amount

The discount amount on the counter proposal.

Discount Schedule

The discount schedule on the response.

Counter Proposal Discount Schedule

The discount schedule on the counter proposal.

Response Discount Code

The discount code on the response.

Counter Proposal Discount Code

The discount code on the counter proposal.

Response Discount Method

The discount method on the response.

Counter Proposal Discount Method

The discount method on the counter proposal.

Net Bidder Price

The net price including bidder landed costs on the response.

Counter Proposal Net Bidder Price

The net price including bidder landed costs on the counter proposal.

Net Price

The net price including all landed costs (bidder and third party) on the response.

Counter Proposal Net Price

The net price including all landed costs (bidder and third party) on the counter proposal.

Purchase Price

The net price on the response.

Price Unit

The unit in which the net price is expressed.

Counter Proposal Purchase Price

The net price on the counter proposal.

Response Delivery Terms

The delivery terms on the response.

Counter Proposal Delivery Terms

The delivery terms on the counter proposal.

Response Point of Title Passage

The point of title passage on the response.

Counter Proposal Point of Title Passage

The point of title passage on the counter proposal.

Payment Terms

The payment terms on the response.

Counter Proposal Payment Terms

The payment terms on the counter proposal.

Gross Amount

The total gross amount on the response.

This amount is calculated as follows:

Supply Quantity * Price Current Response
Counter Proposal Gross Amount

The total gross amount on the counter proposal.

This amount is calculated as follows:

Supply Quantity * Price Current Counter Proposal
Discount %

The total discount percentage on the response.

This percentage is calculated as follows:

Discount Amount Current Response / (Supply Quantity * Price Current Response) * 100%
Counter Proposal Discount %

The total discount percentage on the counter proposal.

This percentage is calculated as follows:

Discount Amount Current Counter Proposal / (Supply Quantity * Price Current Counter Proposal) * 100%
Discount Amount

The total discount amount on the response.

Counter Proposal Discount Amount

The total discount amount on the counter proposal.

Net Amount

The total net amount on the response.

Counter Proposal Net Amount

The total net amount on the counter proposal.

Bidder Landed Costs Amount

The total landed cost amount of all bidder landed cost lines that are linked to the response.

Counter Proposal Bidder Landed Cost Amount

The total landed cost amount of all bidder landed cost lines that are linked to the counter proposal.

Net Amount incl. Bidder Landed Costs

The total net amount including the bidder landed cost amount of the response.

Counter Proposal Net Amount incl. Landed Costs

The total net amount including the bidder landed cost amount of the counter proposal.

3rd Party Landed Costs Amount

The total landed cost amount of all third party landed cost lines that are linked to the response.

Note: Third party landed costs are not negotiable.

Counter Proposal 3rd Party Landed Costs Amount

The total landed cost amount of all third party landed cost lines that are linked to the counter proposal.

Note: Third party landed costs are not negotiable.

Net Amount

The total net amount including all landed costs (bidder and third party) for the response.

It is calculated as follows:


               Net Amount + Bidder Landed Costs Amount + 3rd Party Landed Costs Amount
            

Net Amount incl. Landed Costs

The total net amount including all landed costs (bidder and third party) for the counter proposal.

It is calculated as follows:


               Net Amount + Bidder Landed Costs Amount + 3rd Party Landed Costs Amount
            

Contact

The bidder's contact.

Full Name

The contact's first, middle, and last name.

Office Phone

The phone number at the business address.

Mobile

The contact's mobile phone number.

E-Mail

The contact's e-mail address.

Contact Name

A bidder's informal contact. You can freely specify a contact name in this field.

Contact Phone

A bidder's informal contact phone. You can freely specify a phone number in this field.

Contact E-mail

A bidder's informal contact e-mail. You can freely specify an e-mail address in this field.