Change Request

A change request is created automatically as soon as the supplier updates and submit any information in the portal. For each change, a different change request must be created. The status of the request is updated based on the actions performed by the supplier and the customer. Possible values:

  • Created: The subcontractor initiates the update.
  • In Process: The subcontractor saves the update.
  • Submitted: The subcontractor submits the updated information.
  • Approved: The updated information is approved by the contractor.
  • Incomplete: The contractor requires additional information.
  • Declined: The contractor rejects the changes.
  • Canceled: The subcontractor can cancel the change request if required.