Release Equipment Procurement Order for Utilization

When required task is completed, the Equipment Procurement Order can be released for Utilization. For most Equipment Procurement Orders this is a mandatory activity in the order procedure which can be executed before or after printing. Equipment Procurement Order lines for which the Description Only check box is selected, are released for Utilization too.

You can use the Release for Utilization option in the Equipment Procurement Order Line (tdpur6601m100) session, to access the Release Services Procurement Orders for AFP / Equipment Utilization (tdpur6200m100) session.

During release for Utilization, a Utilization is generated for the entire order. One Utilization can exist with multiple lines.

After an Equipment is released for Utilization, the execution status for the Release for Utilization activity is set to Executed.