Initialize master data

After setting up PLM company, you must initialize the master data using the Initialize Master Data (pdcom9200m000) session.

Note: Until the 2022.12 release, to load the master data, you must refer to the KB 2224293. For the releases later than 2022.12, you can load the master data using the Initialize Master Data (pdcom9200m000) session.

To initialize the master data:

  1. Start the Initialize Master Data (pdcom9200m000) session.
  2. Select the required release version such as 2023.04, 2023.05 and so on.
  3. Select the required modules as applicable.
  4. Click Process to initialize. Master data is initialized for the selected release and module.