cprrp domains

Inventory

Scheduled Receipts

The receipts made for a particular purchase schedule (line) in the Purchase Schedule - Receipts (tdpur3115m200) session.

Item

The item order plan is generated based on all item transactions will be shown, whether the transaction contains a project peg or not. The user can only select an item, and not Project/ Element/ Activity.

Item-Project

The item order plan is generated based on all item - PCA transactions for a selected item - project combination. User can only select item and Project. No Element or Activity can be selected.

Item-Project Peg

The item order plan is generated based on all transactions for specific defined item - PCA combination. the user should be able to define item, Project, Element and Activity.

Plan Item

If this value is selected the Print Subcontracint Forecast report is printed.

Delivery Date

If this value is selected Print Subcontracting Forecast by Delivery Date report is printed.

Plan Item

If this value is selected the Planned Inventory Movements by Item is printed. The Planned Inventory Movements by Item (Item Details) is printed only when the Print Details checkbox is selected.

Order

If this value is selected the Planned Inventory Movements by Order report is printed.

Supplying Item

The lead time can be a production or purchase lead time. The lead time depends on the actual source of the supplying plan item (which can be defined in another company – the supplying company).

Production N.A. Item - Production (tiipd0101m000)
Purchase N.A. Items - Purchase (tdipu0101m000)
Distribution filled Freight Management / Distance tables
empty Supplying Relationships (cprpd7130m000)
Supply Lead Time

The distribution lead times. The distribution lead time is retrieved from the supplying relations or from distance calculations.

Supplying Relation
Carrier Specified Lead time is retrieved in the following order:
  1. Freight Management package
  2. Distance Tables
Carrier Not Specified The lead time as defined in the Supplying Relationships (cprpd7130m000)
To be released

The planned order is ready for transfer to the execution level.

Not to be released

The planned order cannot yet be transferred to the execution level.

Planned

You can still modify the planned order.

Firm Planned

LN does not change the start date or the order quantity of the order if you set the Planning Method field to Forward. LN does not change the finish date or quantity of the order if you set the Planning Method field to Backward.

You can still modify the planned order details.

Confirmed