Resource Order Plan Chart (Modify Chart) (cprrp0731m100)

Use this session to display data from your resource order plan in a graphical format.

To display data:

  1. Specify a scenario and a plan level.
  2. Specify a work center.
  3. Specify the start date, the period length, and the maximum number of periods for the chart.
  4. Specify the type of data you want to view.
  5. Select a chart type.
  6. Click the Show Chart button.

Most types of data shown in the chart correspond to fields in the resource order plan (see the Resource Order Plan (cprrp0530m000) session).

Field Information

Scenario

Specify the scenario for which LN must draw a chart of the planning data for the specified work center.

Scenario

The description of the scenario.

Plan Level

The plan level of the plan items that use the work center for which LN must draw a chart.

Work Center

The work center for which LN must draw a chart.

Start Date

The requested start date for the chart.

Period Length

The period length for the division of the time scale of the chart.

Number of Periods in View

The maximum number of periods shown on the chart.

CTP Reservations

If this check box is selected, the chart displays the capacity used for capacity CTP reservations.

Critical Capacity Requirements

If this check box is selected, the chart displays the capacity used for critical capacity requirements.

Planned Production Orders

If this check box is selected, the chart displays the capacity used for planned production orders.

Production Orders

If this check box is selected, the chart displays the capacity used for production orders.

PCS Activities

If this check box is selected, the chart displays the capacity used for PCS activities.

Service and Maintenance Orders

If this check box is selected, the chart displays the capacity used for service orders and maintenance orders.