Item Order Plan - Find (cprrp0521s000)

Use this session to specify a scenario, a plan item and a period length for which you want to analyse the item order plan.

The result is shown in the Item Order Plan (cprrp0520m000) session.

Field Information

View by
View by

Select how the item orders will be sorted in the Item Order Plan (cprrp0520m000) session.

Allowed values

  • Item
  • Item-Project
  • Item-Project Peg
Scenario

Enter the scenario of which you want to see the item order plan.

Plan Item

Define the plan item for which you want to see the item order plan.

Project

The Project linked to the contract.

Element

The code of the element that is used for project cost pegging purposes.

Activity

The code of the activity that is used for project cost pegging purposes.

Period Length

The length of the period units that are used for the item order plan.

Allowed values

  • 1 Day
  • 7 Days
  • 14 Days
  • 28 Days
  • Detail
  • Plan Periods
Show Order Distribution

If this check box is selected, the order distribution lines for the production order are shown in the Item Order Plan.

Note: 
  • The checkbox is only visible when Project Pegging or Unit Effectivity is implemented.
  • The checkbox can only be cleared when the View by field is set to Item and Period Length is set to Detail.
  • When Project Pegging is not implemented it can only be cleared when Period Length is set to Detail.
  • When cleared in the Item Order Plan no distribution lines will be visible in the Item Order Plan.
Start Date

In this field, you can select the start date for the item order plan from the displayed calendar.

Hide 'Empty' Periods

If this check box is selected, the empty periods are hidden when the results are displayed in the Item Order Plan (cprrp0520m000) session. If, for the plan item, no planned inventory transactions, or safety stock simulated values are present in LN, periods are empty.

Display Cost Peg Transfers
If this check box is selected, the cost peg transfer is displayed.