Print Resource Order Plan (cprrp0430m000)

Use this session to print the resource order plan that you can maintain in the Resource Order Plan (cprrp0530m000) session.

Field Information

Scenario

scenario

Plan Level

plan level

Period Length

The length of the periods to which the values of the work center order plan are aggregated.

If you select the Details check box, LN does not aggregate the values into periods. In that case, individual planned production orders are listed in the report.

Work Center

The work center for which the report is printed.

Critical Capacity Type

The capacity type displayed in the work center order plan.

Allowed values

Labor Capacity

Labor capacity is used in Enterprise Planning to express the capacity use of the resource master plan.

Machine Capacity

Machine capacity is used in Enterprise Planning to express the capacity use of the resource master plan.

If the work center order plan shows the aggregated capacity of main and sub work centers, and this field is set to Machine Capacity, the machine capacity of all involved work centers is aggregated.

Date

Date from which you want to print the work center order plan.

Date

Date up to which you want to print the work center order plan.

Details

If this check box is selected, the report lists the individual planned production orders that utilize capacity.

Hide 'Empty' Periods

If this check box is selected, LN hides the empty periods.

Sorted By

If you selected the Details check box, you can specify the order in which the report shows the planned production orders here.