Plan Unit (cprpd6100m000)

Use this session to display and maintain plan units.

Before you define plan units, you must determine which plan items you want to group to a plan unit, because they must use the same critical materials and the same critical capacities.

You can assign a plan items to a plan unit in the Master Plan Unit field in the Items - Planning (cprpd1100m000) session.

In the Master Planning Method field you can select the master-planning engine that LN must use to plan the plan unit.

Note:  LN does not take into account plan units for order-based planning.

Field Information

Plan Unit

plan unit

Master Planning Method

The master planning engine indicates which optimization algorithm will be used to generate master plans for the plan items of a plan unit.

Note: Specify the hosts and servers for the planning engine in the Planning Parameters (cprpd0100m000) session.

Master Phase Number

The phase number for master planning.

Default value

By default, LN sets the phase number to zero.