Resources (cprpd2501m000)

Use this session to display the different resources used in Order Planning.

Resources are generated when master data is set up for an operational resource such as a work center, subcontractor or supplier.

Field Information

Planning Cluster

The planning cluster for which the resources are defined.

Resource Type

The type of resource that is defined.

Allowed values

  • Work Center
  • Work Cell
  • Work Cell Machine
  • Machine Capacity Group
  • Operation Capacity
  • Production Capacity
  • Supplying Cluster
  • Supplier
Production Site

The ID of the production site to which the resource belongs.

Work Center

The work center ID if the resource type is Work Center, Work Cell, Work Cell Machine or Machine Capacity Group.

Machine Type

The machine type that is part of the resource if the resource type is Machine Capacity Group.

Buy-from Business Partner

The business partner that is part of the resource.

Subcontractor Site

The ID of the subcontractor site that is part of the resource.

Supplying Company

The ID of the supplying company that is linked to the resource.

Supplying Cluster

The ID of the supplying cluster to which the resource is linked.

Ship-from Business Partner

The ID of the business partner the resource is shipped from.