Resource Capacity (Machine Capacity) (cprpd2102m100)

Use this session to display machine capacity group capacity details. The graph shows the capacity of the calendar working hours per week, up to eight weeks.

Field Information

Resource

The resource ID.

Resource Type

The type of resource.

Capacity Type

The type of capacity that applies to the resource.

Allowed values

  • Labor
  • Machine
  • Item
Capacity Type Unit

The unit type in which capacity is defined.

Allowed values

  • Hours
  • Days
Capacity Type Bucket

The length of a capacity bucket: one week.

Machine Type

The machine type that is part of the resource.

Work Center

The work center that is part of the resource.

Production Department

The production department that is part of the resource.

Production Site

The site that is part of the resource.

Planning Cluster

The cluster the resource to which the resource belongs.

Critical

If this check box is selected, the selected capacity is critical to planning.

Available Machines

The number of machine available to the selected resource.

Actual Calendar

The actual calendar used by the selected resource.

Origin

The source of the calendar.

<

The button to move the graph to the left.

>