Plan Items - Optimized Lot Sizes (cprao3110m000)

Use this session to view the optimized lot sizes and order intervals that LN calculated in the Optimize Lot Sizing (cprao3200m000) session.

Field Information

Scenario

The scenario for which LN displays the optimized lot sizes and order intervals.

Plan Item

The plan item for which LN displays the optimized lot sizes and order intervals.

Order Interval

The optimized order interval for the specified plan item.

The order interval is expressed in calendar days.

Use the Copy Lot Sizes to Item Ordering Data option from the appropriate menu to copy the optimized order interval to the Order Interval field in the Items - Ordering (tcibd2100m000) session.

Lot Size

The optimized lot size for the specified item

Select the Copy Lot Sizes to Item Ordering Data option from the appropriate menu to copy the lot size to the Economic Order Quantity field in the Items - Ordering (tcibd2100m000) session.

Old Lot Size

The lot size before optimization.

Work Center

The resource for which the item parameters are optimized.

If the routing of an item contains multiple resources, this field displays the resource with the highest priority.

Computed Cost

The cost associated with this parameter setting.

Note: This is the cost over the total time period for which the logistic parameters have been optimized.

Cost Advantage

The difference between the cost of the optimized lot size and the cost of the currently effective lot size.

The currently effective lot size is defined in the Items - Ordering (tcibd2100m000) session.

This field indicates the cost advantage that can be realized if you copy the optimized parameters to the Item Base Data module.

Note: The cost is calculated for the total time period over which the logistic parameters were optimized.