Transfer Planned Production Orders (cppat1211m000)

Use this session to transfer the selected range of planned production orders to the Job Shop Control module.

Field Information

Actual Scenario

actual scenario

LN only transfers planned orders for the actual scenario.

Planned Order Group

If this check box is selected, Enterprise Planning transfers the production order group specified in the Planned Order Group field, which is also a part of Production data.

Note: You can create a production order group in the Create Order Group for Planned Orders (cppat3250m000) session.

Job Shop

If this check box is selected, LN transfers the selected range of planned production orders to the Job Shop Control module.

Note: If this check box is selected, LN does not transfer planned production orders that belong to an order group.
Ordering Site

The code of the site.

From Plan Item

The From and To fields define a range of: plan items for which LN must transfer the selected order types.

To Plan Item

The From and To fields define a range of: plan items for which LN must transfer the selected order types.

Item Group

The From and To fields define a range of: item groups.

Warehouse

The From and To fields define a range of: warehouses.

Planner

The From and To fields define a range of: planners.

Product Class

The From and To fields define a range of: product lines.

Selection Code

The From and To fields define a range of: selection codes.

Planned Start Date

The From and To fields define a range of: dates, on which the order is planned to start.

Planned Finish Date

The From and To fields define a range of: dates, on which the order is planned to end.

Shop Floor Planner

The From and To fields define a range of: shop floor planners.

Routing Group

The From and To fields define a range of: routing groups.

Interactive

If this check box is selected, LN does not immediately transfer the orders, instead starts the Select Order Planning for Transfer (cppat0210m000) session.

In the Select Order Planning for Transfer (cppat0210m000) session, you can modify or confirm the selection of the planned orders.

If this check box is cleared, LN directly transfers the selected orders.

Include Items to be Customized

If this check box is selected, you can also transfer planned orders, production plans and purchase plans for items for which the Customizable check box is selected in the Items (tcibd0501m000) session and the project segment is empty.

You cannot select this check box if the Interactive check box is cleared.

Transfer Text As Well

If this check box is selected, LN transfers the text linked to the planned order line.

You can link a text to a planned order line in the Planned Orders (cprrp1100m000) session.

Transfer Status Planned as Well

If this check box is selected, LN transfers the planned orders with the order status Planned.

Note: Generally, LN only transfers planned orders with order status Confirmed.
Transfer Status Firm Planned as Well

If this check box is selected, LN transfers the planned orders with the order status Firm Planned.

Note: Generally, LN only transfers planned orders with order status Confirmed.
Transfer Orders Planned by Infor Planning

If this check box is selected, LN transfers the planned orders planned by shop floor planners.

Transfer Limitations

If this check box is selected, the batch with the planned orders are transferred.

Priority based on

The priority based on which the planned orders must be transferred.

Select a priority from the below options:

  • Planned Finish Date
  • Planned Order Number
  • Planned Start Date
Transfer Batch Size

The batch size of the transferred batch.

Direct Release after Transfer

If this check box is selected, the planned orders are directly released to the execution level.

Process Report

If this check box is selected, LN generates a process report.

The process report contains all the orders that are processed together with their order number and the corresponding Job Shop Control order, purchase order and warehouse order numbers.

Error Report

If this check box is selected, LN generates an error report.

Use specific Devices

If this check box is selected, you can select a specific device to print the report.

Planned Production Orders

The From and To fields define a range of: planned production orders.

Production Order Series

The From and To fields define a range of: product order series.

Planned Order Group

The From and To fields define a range of: the order groups of the planned orders in the Enterprise Planning .

Create Production Order Group

If this check box is selected, the planned orders are transferred to a order group created in Job Shop Control .

If this check box is cleared, LN disbands the EP order group, and transfers the planned orders individually.

Production Order Group Series

The series defined for JSC order group.

Production Order Series