Reporting Capacity CTP of Items by Resource

This session reports the capable-to-promise for all items that have this resource specified in the item's bill of critical capacities (BCC).

The reports contains the following information:

  • The delivery period: the period for which you want to check the quantity of plan item that can be delivered.
  • The cumulative capacity CTP of the specified resource in the specified period.
  • The capacity CTP of the resource in the specified period.
  • The cumulative ATP of the involved plan items in the specified period.
  • The critical work center.

The reported CTP values are the sum of:

  • The item's cumulative ATP
  • The resource's cumulative capacity CTP divided by the capacity that is required for the item (according to the item's BCC)
Note: If the resource's cumulative capacity CTP is negative, it is not taken into account.