General lead times
The following table lists the lead time components, the calendar, and availability type that are used to plan the general lead times.
Lead time component | Sequence to find calendar: |
---|---|
Safety time (BP) |
|
Safety time (item) |
|
Extra lead time |
|
Inbound lead-time |
|
Outbound lead-time |
|
Safety time and extra lead time use the calendar linked to the plan item. The calendar is retrieved as follows:
- Enterprise unit of plan item in the Items - Planning (cprpd1100m000) session
- Company calendar in the Companies (tcemm1170m000) session
Warehouse inbound and outbound times are linked to the (item-) warehouse data of the planned order. The warehouse calendar is used to calculate inbound and outbound times.