Distribution order lead times

The following tables list the lead time components, the calendar, and availability type that are used to plan the distribution order lead times.

Lead time component (with carrier) Sequence to find calendar code: Sequence to find availability type (AT):
Transportation time (transport part)
  1. Means of Transport
  2. Buy-from BP of Carrier
  3. Company
COM parameters
Transportation time (loading/unloading) Address Company COM parameters
Lead time component (without carrier) Sequence to find calendar:
Supply time (Distribution)
  1. Department of Resource
  2. Production Department

To plan a distribution order, you always use a supplying relationship. If a carrier is linked to the supplying relation, to perform the order offset, you can use transportation time. Otherwise, the supplying relationship supply time is used.

Supply time

For the planning of supply time, you can use the calendar of the supplying relationship’s supply source in the Supplying Relationships (cprpd7130m000) session. The calendar is retrieved as follows:

  1. Calendar of the department of the resource.
  2. Enterprise unit of the department in the Enterprise Units (tgbrg0130s000) session
  3. Calendar of the production department.

If no supply resource is defined, the item calendar is retrieved as follows:

  1. Enterprise unit of the plan item in the Items - Planning (cprpd1100m000) session
  2. Company calendar in the Companies (tcemm1170m000) session