Conversion Parameters for Enterprise Planning (bcmcp1100s000)

Use this session to enter pre-conversion parameters that will be used during conversion of Enterprise Planning.

Execution

Always mandatory before the conversion of Enterprise Planning.

Actual Scenario

Enterprise Planning can make use of different (simulated) scenarios. There must be 1 scenario in use for the actual planning. The field Actual Scenario is pointing to the actual planning scenario.

Default value

The Default value is ACT

Default Availability Type

In LN calendars (module tcccp) different availability can be defined per calendar. Other modules that make use of the central calendars needs to be pointed to the availability that is used. In the field Default Availability Type the used availability type must be entered.

Scenario Start Date

The Start Date for the planning scenario. Enterprise Planning is only calculating in the time horizon between Plan Start Date and Plan Finish Date. Plan Start Date must be in the past. The value depends on the oldest back orders date or required history for forecast calculations.

Scenario Finish Date

The Finish Date for the planning scenario. Enterprise Planning is only calculating in the time horizon between Plan Start Date and Plan Finish Date. Plan Finish Date must be in the future. The value depends on the maximum lead time.