Creating or updating Tools in Depot Repair application

  1. Select the required work order from the list of available work orders.
  2. Select the required activity in the Activity screen.
  3. Select the Tools screen.
  4. Click Add to create a new tool.
  5. Specify this information:
    Work Order/ Activity Line
    The code of the work order.
    Activity Status
    The status of the Activity. Possible values:
    • Free
    • Planned
    • Released
    • Completed
    • Signed-Off
    • Transferred
    • Closed
    • Canceled
    Cost Type
    The type of costs for the activity. Possible values:
    • Tooling
    • Other
    Item
    The code and description of the items available for the selected work order.
    Note: You can specify the first three characters of the item to retrieve the item from the list of available items.
    Estimated Quantity
    The estimated quantity that is required to carry out the work order or the activity.
    Actual Quantity
    The quantity used for the work order or for the work order activity.
    Checked-Off
    If this check box is selected, this resource line is checked off and can no longer be modified.
  6. Click CHECK-OFF to check off the tools details.
  7. Click SAVE to create or update tools in Infor LN.