Print Actual Production Costs (ticst0415m000)
Use this session to print a report with material costs, operation costs, subcontracting costs, and standard cost surcharges for the actual costing of production orders.
You can print:
- All costs by project/production order.
- All costs by main item in a specific period.
- All costs by a department in a specific period.
LN prints the actual costing data stored in the Job Shop Financial Transactions (ticst3500m000) session or the PCS Financial Transactions by Origin (tipcs3500m000) session.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Selections
-
- Select Print Method
-
Specify how the costs are grouped on the report.
Allowed values
- Order
- Project (PCS), Order
- Project Peg, Order
- Department, Transaction Date
- Main Item, Transaction Date
- Selection Range
-
- Project (PCS)
-
If this check box is selected, chose the range of Projects (PCS) for which actual production costs are printed.
- Project
-
If this check box is selected, chose the range of Projects for which actual production costs are printed.
- Element
-
If this check box is selected, chose the range of Elements for which actual production costs are printed.
- Activity
-
If this check box is selected, chose the range of Activities for which actual production costs are printed.
- Production Order
-
If this check box is selected, chose the range of Production Orders for which actual production costs are printed.
- Costing Work Center
-
If this check box is selected, chose the range of Costing Work Centers for which actual production costs are printed.
- Transaction Date
-
If this check box is selected, chose the range of Transaction Dates for which actual production costs are printed.
- Main Item
-
If this check box is selected, you can specify a range of items for which actual production costs are printed.
- Settings
-
- Currency for details
-
Select in which currency the costs must be printed.
Note:- If the Currency System of your company is Single or Dependent, this field is enabled.
- If the Currency System of your company is Independent, this field is disabled and displays Reference.
Allowed values
- Reference
- Calculation Office
-
The currency of the calculation office
- Department or Warehouse
- Currency Total
-
Any other currency.
- Currency for totals
-
LN prints the cost amounts in this currency.
Note:- In the Currency for details field you can select in which currency the costs must be printed.
- If you select Currency Total in the Currency for details field, you can enter a currency in this field.
- Exchange Rate Type
- Detail Level
-
- Group by
-
- Detail Level
-
Select how the actual costs are grouped:
Allowed values
- By Cost Type
- By Cost Component
- By Transaction Date
- Options
-
- Print Closed Orders Only
-
If this check box is selected, only orders with the Closed status are printed.
- Exclude Already Printed Orders
-
If this check box is selected, LN only prints orders that were not printed before.
- Include Customer Owned
-
If this check box is selected, customer owned materials are included in the report.
-
- Material Costs
-
If this check box is selected, LN prints material costs in the report.
- Subcontracting Costs
-
If this check box is selected, LN prints subcontracting costs in the report.
- Operation Costs
-
If this check box is selected, LN prints operation costs in the report.
- Surcharges
-
If this check box is selected, LN prints the surcharges in the report.