Concept Activation (tcemm4600m100)

Use this session to view and maintain the overall concepts for which an activation process is required.

Field Information

Multisite

The multisite overall concept.

Status

The activation status of the multisite overall concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Kanban Integration

The kanban overall concept.

Status

The activation status of the kanban overall concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Extended Tax Configuration

The extended tax-configuration overall concept. For more information on the activation of the Extended Tax Configuration, refer to LN Extended Tax Configuration User Guide.

Status

The activation status of the extended tax-configuration overall concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Extended Registration Management

The extended tax registration management overall concept. For more information on the activation of the Extended Registration Management, refer to LN Extended Registration Management User Guide.

Status

The activation status of the extended tax registration management overall concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Extended SBI Configuration

The extended SBI configuration overall concept.

Status

The activation status of the extended SBI configuration overall concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Services Procurement

The services procurement overall concept.

Status

The activation status of the services procurement concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.
Buying Equipment

The buying equipment overall concept.

Status

The activation status of the buying equipment concept.

Allowed values

Inactive

The initial status of the overall concept. The activation process has not yet started.

In Preparation

One or more of the concepts of the overall concept have been set to status In Preparation. This means that the preparation stage of the master data and parameter setup of these concepts has started.

The other concepts of the overall concept have status Active or Inactive.

Partially Active

One or more of the concepts of the overall concept have been set to status Active.

The other concepts of the overall concept have status Inactive.

Active
All concepts of the overall concept have been set to status Active.