Delete Resource Capacity Calculations (cprpd2203m100)

Use this session to delete resource capacity calculations that are generated. The date is determined based on a defined retention period, expressed in days, weeks, or months.

Note: By default, the retention period and unit specified in the Retain Resource Capacity Calculation for field in the Planning Parameters (cprpd0100m000) session is considered.

Field Information

Up to Date
The period up to which the data must be deleted.

The unit in which the data deletion period is expressed..

Allowed values

Days
The retention period is expressed in days. You can use this option for short-term operational planning and recent data snapshots. Maximum of 30 days can be specified.
Weeks
The retention period is expressed in weeks. You can use this option in alignment with production planning horizons (quarterly ≈ 3 months). Maximum of 12 weeks can be specified.
Months
The retention period is expressed in months. You can use this option to ensure traceability for annual audits and regulatory compliances. Maximum of 12 months can be specified.
Not Applicable
Only not completed runs
If this check box is selected, the unfinished calculations within the date range are deleted, and the completed runs are retained.
Settings
Print Error Report
If this check box is selected, an error report is printed when the data is not processed successfully.