Process Project Cost Peg Transfers (whinh1240m100)
Use this session to process the generated cost peg transfers.
Field Information
-
- Origin
-
cost peg transfer origins.
- Project Cost Peg Transfer
-
the cost peg transfer numbers.
- Line
-
the cost peg transfer line numbers.
- From Project
-
projects from which the cost pegs are transferred.
- From Element
-
elements linked to the project.
- From Activity
-
activities linked to the project.
- To Project
-
the projects to which the cost pegs are transferred.
- To Element
-
the elements linked to the project.
- To Activity
-
the activities linked to the project.
- Effectivity Unit
-
effectivity units.
- Warehouse
-
the warehouses.
- Reason
-
reason codes for cost peg transfer.
- Planned Transaction Date
-
the dates on which the target peg requires cost peg transfer is processed.
- Item From
-
items.
- Item To
-
items.
-
- Success Report
-
LN prints the processed cost peg transfer orders.
- Error Report
-
LN prints a report of the errors that occur during the cost peg transfer.