Process Project Cost Peg Transfers (whinh1240m100)

Use this session to process the generated cost peg transfers.

Field Information

Origin

cost peg transfer origins.

Project Cost Peg Transfer

the cost peg transfer numbers.

Line

the cost peg transfer line numbers.

From Project

projects from which the cost pegs are transferred.

From Element

elements linked to the project.

From Activity

activities linked to the project.

To Project

the projects to which the cost pegs are transferred.

To Element

the elements linked to the project.

To Activity

the activities linked to the project.

Effectivity Unit

effectivity units.

Warehouse

the warehouses.

Reason

reason codes for cost peg transfer.

Planned Transaction Date

the dates on which the target peg requires cost peg transfer is processed.

Item From

items.

Item To

items.

Success Report

LN prints the processed cost peg transfer orders.

Error Report

LN prints a report of the errors that occur during the cost peg transfer.