Job Shop Planning Board (tisfc8372m000)

A shop floor planner can use this workbench to manually change the schedule of operations for balancing the supply and demand.

The schedule of operations can also be changed manually when:

LN defaults the Site in this workbench from the Production User Profiles (timfc0120m000) session if the multisite functionality is implemented.

Related topics
Job Shop Planning Board
Job Shop Planning Board toolbar
Job Shop Planning Board user settings
Job Shop Planning Board Workbench Gantt
Job Shop Planning Board Workbench Material Availability
Job Shop Planning Board Workbench Capacity