Report Shift (tisfc4112m000)
You can view additional data in these sessions:
- Machine Operation Quantities (tisfc4101m000)
- Correct Machine Operation Quantities (tisfc4101m200)
- Machine Hours (tisfc4102m000)
- Machine Time Stamps (tisfc4111m000)
Field Information
-
- Site
-
The site ID.
- Production Department
-
Select the range of production departments for which you want to view machine operations.
- Supervisor
-
Select the range of employees for who you want to view the machine operations. Each employee is responsible for one or more work centers.
- Work Center
-
Select the range of work centers for which you want to see machine operations.
-
- Released
-
machine orders with the status Released and their number are displayed.
- Active
-
machine operations with the status Running and their number are displayed.
- Completed
-
machine operations with the status Finished and their number are displayed.
-
- Past
-
shifts closed before the current date are displayed.
- Current
-
shifts currently active are displayed.
- Future
-
shifts with the start date in the future are displayed.
-
- Machine Number
-
The machine designation.
- Production Order
- Operation
-
The operation ID.
- Machine Sequence
-
The sequence number of the machine operation.
- Item
-
The end item produced.
- Planned
-
The total quantity of product required.
- Planned
-
The quantity of product planned for production.
- Completed
-
The quantity of product completed.
- Rejected
-
The quantity of product rejected during the shift.
- Unit
- Planned Finish
-
The date and time the employee finishes work on the project activity.
- Shift
-
The shift ID.
- Shift (GUID)
-
The unique ID for the shift.
- Shift Start Date
-
The date and time the selected shift started.
- Shift End Date
-
The date and time the selected shift ended.
- Shift Aggregated
-
the selected shift capacity was aggregated to work center.
- Machine Hours Posted
-
machine hours have been posted.
- Shift Completed
-
The date and time the selected shift was reported completed.
- Quantity Reporting is Completed
-
all quantities have been reported for the selected shift.
- Aggregated to Operation
-
machine hours have been aggregated to operation.
- Machine Operation Status
-
The status of the machine is:
- Released
- Setup
- Running
- Interrupted
- Finished
- Closed
- Initial
- Site
-
The ID of the site.
- Production Department
- Supervisor
-
The name of the employee responsible for overseeing the shift.
- Work Center
-
The work center ID.
- Machine Type
- Shift in Planning
-
the machine operation has been replanned. If the check box is cleared the machine operation can be shifted in planning if the machine operation has not yet started.