Automated Queue Time Compression (tisfc1103s000)
Use this session to evenly remove the queue time from all the operations of a production order that are not yet completed. In this way, you could meet a production order's modified delivery date or start date.
Queue time compression is supported for forward planning methods as well as for backward planning methods.
After you have selected a production order to compress in the Production Planning (tisfc0110m000) session, you can adjust the following options:
- Target Start Date and Target Finish Date
- Queue Compression Method
- Targeted Compression %
- Include Operations at Critical Work Center
Field Information
- Production Order
- Clustered Line Station Order Status
-
The status of the production order.
- Item
-
The item that is produced by the production order.
- Description
-
The item's description that is produced by the production order.
- Operation
-
The first operation of the production order that has not been reported as completed. This operation's start date is the date in the Operation Start Date field.
- Move Start Date
-
The earliest date that the last operation that is not yet reported as completed can be completed, plus the queue time.
- Operation
-
The last operation of the production order that has not been reported as completed. This operation's finish date is the date in the Move Start Date field.
- Target Finish Date
-
The date that you want to complete production after the compression process.
Note: Depending on your selection in the Queue Compression Method field, you may not reach the target. - Queue Compression Method
-
The method which LN uses to evenly remove slack from the operations' queue times.
Note: The operations should not yet reported as completed. - Targeted Compression %
-
The maximum or actual value by which queue time is reduced.
If you chose the Best Fit method:
- The maximum value by which the queue time is reduced
If you chose the Targeted Percent method:
- The actual value by which the queue time is reduced
- Include Operations at Critical Work Center
-
the queue times of bottleneck work centers are compressed when you run this session.
Note: You can define a work center as critical in master planning in the Work Centers (tirou0101m000) session. - Planning Method
-
When you use this session to remove slack from queue times, LN replans the order dates using the method in this field.
- Forward
-
For a production order, the planning of the production order is based on a fixed start date. A delivery date is calculated from the order run time.
For a project, the network planning for the project is executed on the basis of a fixed start date. When you start the planning in the Generate Network Planning (tppss2240m000) session, LN determines the project's delivery date with a Forward planning method.
- Backward
-
For a production order, the planning of the production order is based on a fixed delivery date. A start date is calculated from the order run time.
For a project, the network planning for the project is executed on the basis of a fixed delivery date. When you start the planning in the Generate Network Planning (tppss2240m000), LN determines the project's start date with a Backward planning method.
- Item Safety Time
- Production Start Date and Time
-
The date you plan to start work on the production order.
- Extra Lead Time
- Requested Delivery
-
The date the customer wants the production order to be delivered.
- [H]
-
The total queue time of the production order.
- Planned Delivery
-
The Planned Delivery Date for the production order. After you have compressed the queue times (if you use the Best Fit method and Forward planning), LN will alter this date.
- [H]
-
The estimated number of hours required to complete the production order, including planned queue time.
- Confirmed Delivery
-
The Confirmed Delivery for the production order. After you have compressed the queue times (if you use the Best Fit method and Forward planning), LN will alter this date.
- Setup Remaining As % of Run
-
The total setup time of the production order as a percentage of the total run time of the order.
- Inbound Lead Time
- Outbound Lead Time
- Inbound Lead Time
- Outbound Lead Time
- Including Queue Times in Hours
-
The queue times in a production order can be expressed in hours as well as in days.
only the queue times that are expressed in hours are included the queue time compression.
- Including Queue Times in Days
-
The queue times in a production order can be expressed in hours as well as in days.
only the queue times that are expressed in days are included the queue time compression.
- Including Queue Times in Hours
-
The total of the production order's queue times that are expressed in hours.
- Including Queue Times in Days
-
The total of the production order's queue times that are expressed in days.