Repetitive Settings History by Site (tirpt0181m000)
Use this session to view the history of the repetitive manufacturing settings for a specific site.
Field Information
- Site
-
- Site
- External
-
the planning cluster is linked to subcontractor sites or the planning cluster is used in planning for VMI Forecast.
This depends on the settings of these check boxes:
- Holds Subcontractor Sites
- Customer Site
- Address
- Logistic Company
- Repetitive
-
- Effective Date
-
The date and time the parameters were adjusted.
- Last Changed by
-
The code of the employee who made the last changes to the repetitive parameters.
- Text
-
additional text is present.
- .
-
- Use Global Repetitive Parameters
-
the global repetitive parameter data is used for the site. Consequently, changes to product data at company level are synchronized automatically to the site level.
- Repetitive Production Schedules
-
- Repetitive Production Schedules
-
repetitive production schedules are used to manufacture the product.
Note: Mandatory for items with default supply source Repetitive. - Production Model Series
-
The default series that is used to generate production model codes.
- Series for Manual Schedule Creation
-
The default series used when manually generating production schedules in Repetitive Manufacturing .
- Series for Manual Schedule Creation
-
The series that is used by Enterprise Planning to generate production schedules in Repetitive Manufacturing .
- Series for Warehousing Orders
-
The series that is used to generate warehousing-order numbers.
- Series for Work Cell Cost Documents
-
The default series used for creating work cell cost documents.
- Work Cell Cost Document Duration
-
Specify the duration of the schedule line.
Note:The duration can be:
- Day
- Week
- 4 Weeks
- Month
- Generate Serial Numbers
-
Specify when the serial numbers for a schedule line are generated.
- Manually
- On Release
- Material Backflushing Method
-
The value of this field determines the degree of user interaction when backflushing is carried out.
Allowed values
- Automatic
-
Backflushing of materials and hours is carried out automatically in the background when reporting an operation or production order complete, without prompting the user.
- Interactive
-
When you report an operation or production order as complete, a prompt is displayed. You can click Yes to backflush for the completed quantity or click No to skip backflushing. You can backflush manually later.
- Manual
-
Reporting an operation or production order as complete does not trigger backflushing. To backflush separately, you can use the Backflush Materials and Hours (tisfc0220m000) session or batch processing.
- Automatic Work Cell Hours
-
automatic registration and booking of actual work cell hours is active.
- Work Cell Hours Method
-
The method by which the work cell hours are determined.
-
Register Work Cell Hours
Hours logged by the user. -
Backflushing Hours
A theoretical process time based on reported completed and rejected items.
-
- Backflushing without Warehouse Orders
-
materials are backflushed without warehouse orders to issue material inventory.
- Automatic Labor Hours
-
automatic registration and booking of actual labor hours is active. The Labor Hours hours in the Report Shift (tirpt4636m200) session are automatically copied and booked to the Actual Labor Hours in the Shift - Hours (tirpt4138m000) session.
Note: Labor hours do not have a method option and are always registered. - Progress Tolerance
-
The progress of the process variable in percentages.
- Report on Work Stations
-
schedule lines are reported completed at work station and work cell levels.
schedule lines are only reported completed on work cell level.
Note: Reporting completed is mandatory at work stations marked as count points. - Work Station Machines
- The machine linked to a Work Station.
- Repair Process
-
items can be send for repair during manufacture.
- Multi-Product Production
-
use of production models for multiple end products is implemented.
- Scheduling Process
-
- Allow Offloading
-
offloading of planned runs to work cells with later need dates is possible.
- Move and Swap Lines
-
you can move and swap lines within a run.
- Move and Swap Runs
-
you can move and swap scheduled runs.
- Offload Runs
-
selected runs are offloaded to other work cells.