Copy Routing (tirou2201m000)
Use this session to copy one or more operations from one routing (source) to another (target).
To copy the data of an item routing, select the routing (code) and the item. If the source routing concerns a standard routing, only select a routing (code). You can:
- Copy routing data and retain the data of the target routing. The copied data is added to the target routing.
- Copy routing data and overwrite the data of the target routing.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Manufactured Item
-
Select the manufactured item.
- Routing
-
Select the routing that you want to copy.
- Operation
-
The operation you want to copy to the target item.
- Effective Date
- Expiry Date
- Manufactured Item
- Routing
-
Select the target routing.
- Copy
-
- Copy Process
-
Specify the way the copied data is handled.
- Add and Renumber
-
The copied routing data is added to the target routing.
Note: LN uses incremental steps equal to 10 when copying routing information. - Overwrite
-
The copied routing data overwrites the routing data of the target routing. Only the operations within the selected range are overwritten.
- Step Size
-
Specify size of the step for adding operations to the routing. A smaller step allows for more sub-operations to be added. Specifying the step size lowers the risk of running out of operation numbers.
- Effectivity Statements
-
all exceptions are copied to the target routing.
- Tooling
-
tooling data is copied.
- Activities
-
the activities assigned to the routing are copied to the target routing. This option is only available if both the source and the target are customized items.
- Process Variables
-
process variables are copied.
- Operation Steps
-
operation steps are copied to the target routing.
- Instructions
-
instructions are copied.
- Setup Classes and States
-
setup class and setup state are defined.
- Reference Designators
-
reference designator are copied.
- Skills
-
the skills are copied.