Print Standard Cost Comparison (tipcs3470m000)

Use this session to print the standard cost comparison of two projects. Specify two projects and the amount types you want to compare.

Field Information

Calculation Group

calculation group

First Project

Enter the project for which you want to compare the standard cost with the standard cost of another project.

Amount Type

The amount type of the first project you want to compare with the amount type of the second project.

Second Project

Enter the project for which you want to compare the standard cost with the standard cost of the first project you entered.

Amount Type

The amount type of the second project you want to compare with the amount type of the first project.

For example, you can compare the estimated costs of project one to the budgeted costs of project two.

Standard Cost Calculation by Project

From Cost Difference

Only the components that differ by a percentage that is greater than or is equal to the percentage you entered in the From Cost Difference field are printed.

Include Fixed Costs in Project Valuation

fixed costs are included in the valuation price of the projects which are compared.

Print Difference Only

only the differences greater or equal the percentage you entered in the From Cost Difference field are printed.