Intermediate Results Calculations (ticst0560m000)

Use this session to to manage intermediate results calculations for production orders per site.

Field Information

Production Order

production order

Site

The site ID.

Note: Only visible if multisite functionality is active.

Multisite overview

Calculation Date

The date on which the intermediate results are calculated.

Results Percentage Calculation Method

The method used for the results percentage calculation.

Actual/Estimated Quantity

The produced quantity of end items received in warehouse, compared to the planned order quantity.

By Operation

Variances are booked according to the progress of individual operations.

Actual/Estimated Cost

The amount of actual (production) cost currently booked for the production order, in comparison to the estimated production cost.

Order Progress Percentage

The progress of completion for the selected order in percentages.

Posted to Warehouse

the financial transactions have been posted to the relevant warehouse.

Included Calculation Office Variances

calculation office variances are included in the calculation.

Related topics
Intermediate Results Calculations