Print Estimated vs Actual Production Order Costs (ticst0403m000)

Use this session to print a reports that summarizes a production order's estimated costs and actual costs.

The report contains the following:

  • Material costs
  • Man hour costs
  • Subcontracting costs
  • End item receipt costs

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Multisite overview

Production Order

production order

Production orders - functional overview

Currency for details

Select in which currency the detailed costs must be printed.

Reference

reference currency

Calculation Office

The currency of the calculation office

Department or Warehouse

local currency

Currency Total

Any other currency.

Note: 
  • If the Currency System of your company is Single or Dependent, this field is enabled.
  • If the Currency System of your company is Independent, this field is disabled and displays Reference.

Currency systems

Print Closed Orders Only

LN only prints production orders with the Closed status.

Financial Data

costs and results are printed by material and operation. In addition, costs and results are printed summarized by production order.

For closed orders, the calculation results and production results are printed. Note that these results are calculated based on costs only. The results do not equal the variances that you can view in the Job Shop Financial Transactions (ticst3500m000) session, which are based on costs and receipt amounts.

The results are calculated as follows:

  • Calculation results

    Estimated costs – (standard cost * quantity delivered)
  • Production results

    (Estimated costs – actual costs) – calculation results

only estimated and actual quantities for materials and operations are printed.

Print Actuals Details by Operation

and also the Financial Data check box is selected, the hours costs of operations are split up into man hours costs, machine hours costs, and overhead costs.

and the Financial Data check box is cleared, estimated and actual hours are split up into man hours for setup, man hours for production, machine hours for setup, and machine hours for production.

Print corrected Estimates (based on progress)

the estimated costs are corrected based on the progress of the operation. Material costs are corrected based on the progress of the operation that is linked to the material.

Related topics
Estimated and actual material costs
Production order costing in JSC