Where-Used Job Shop List of Materials Use up Items (tibom3110m200)

Use this session to manage use-up materials in the job shop bill of material.

Note: To use this session the Job Shop by Site parameter in the Concept Activation (tcemm4600m000) session must be set to Active.

Field Information

Use-Up Item

The material from the previous BOM revision, which is now a use-up material. As long as the use-up material is present in inventory, it will be used instead of the material specified in the Item field.

Site

The site ID.

Product

The product ID.

Bill of Material

The ID of the bill of material (BOM) for which the list of material is displayed.

Bill of Material (BOM)

Revision

The bill of material revision.

BOM Quantity

BOM quantity

Position

The number of the JSBOM line.

Item

The material ID.

Warehouse

The warehouse ID.

Lot Selection

If the item is lot controlled, you can select how the material must be issued.

Note: 
  • The Lot Controlled check box in the Items (tcibd0501m000) session must be selected for the item.
  • If the Lot Controlled check box is cleared, the Lot Selection field displays Any and is disabled.

Lot control

Net Quantity

net quantity

Scrap Quantity

The scrap quantity expected during production, independent of the order quantity. This is used to define the amount of material lost every time production is started, for example to test equipment.

Note: This value is defaulted from the Scrap Quantity in BOM Unit field, if the Use BOM Units check box is selected.
Scrap Percentage

The expected relative material loss, for example due to faulty components. The gross quantity should be increased to compensate for these material losses.

Length

This field can be used, together with the Width field and number of units, to calculate the net quantity.

The net quantity is the Length field multiplied by the number of units and multiplied by the Width field, if applicable.

In the Print Production Order Documents (tisfc0408m000) session, you can only print a sawing list if you have entered the Length field for the given component. If you have entered both the Length field and the Width field, you can print a cutting list.

Calculating net quantity

Width

This field can be used, together with the Length field and number of units, to calculate the net quantity.

The net quantity is the Length field multiplied by the number of units and multiplied by the Width field, if applicable.

If you have entered both the Length field and the Width field, you can print a cutting list in the Print Production Order Documents (tisfc0408m000) session.

Calculating net quantity

Size Unit

The unit of measurement used.

Number of Units

The number of times that the required quantity of the material, specified in the Length field and/or the Width field, appears in the product.

Calculating net quantity

Operation

The ID of the operation where the material is used.

M-R Relations Present

material-routing relationships are present for the JSBOM component.

Phantom

the material or component is a phantom.

Text

text about the material is present.

Alternatives Present

alternative materials are linked to the JSBOM line.

Allow Multiple Alternatives

LN can distribute the net quantity of the material over multiple items. For example, the net quantity can be divided over the use-up material and the standard material or over the standard material and one or more alternative materials. LN issues only a single item for this BOM line for one production order.

For examples, refer to Searching for alternative materials.

Using up remaining stock of outdated items

Print on Order Document

the JSBOM component is printed on the order document.

Standard Configuration

the JSBOM line is part of the product's standard configuration.

Note: When using unit effectivity, unit 0 represents the standard configuration.

To reuse the standard items

Exceptions Present

the JSBOM line has exceptions linked to it. Exceptions are part of the unit effectivity concept.

Reference Designator Present

reference designators are present for the item.

Specify Material Offset

you can specify the lead-time offset.

Material Offset

The lead-time offset. LN uses the lead-time offset in capable-to-promise calculations. The date that a component must be available is calculated by subtracting the lead-time offset from the requirement date of the end item.

Note: You can only type the lead-time offset if the Specify Material Offset check box is selected.
Material Offset Unit

Select Hours or Days as the time unit in which you want to express the lead-time offset.

Component CTP

Supplied by Subcontractor

If you subcontract one or more operations, or an item's entire production process, you can choose whether or not to send material to the subcontractor to use for the subcontracted item.

the material is not sent to the subcontractor, but it is supplied by the subcontractor. Therefore, the material's planning and costing is not taken into account.

and the material is linked to a subcontracted operation, the material is sent to the subcontractor.

Overview of subcontracting

Inherit Demand Peg

If a production order is transferred from Enterprise Planning to Job Shop Control , the order can have a demand peg.

Note: A specification is generated for the peg.

You can use this field to determine whether the material must have this demand peg as well.

Customer Furnished Material

the material is a customer furnished material.

Note: Only visible when the Customer Furnished Materials parameter are selected in the Implemented Software Components (tccom0100s000) session.

Customer furnished materials

Contains Customer Furnished Material

the end-item is an item that is built using one or more customer furnished material.

Customer furnished materials

Percentage Required

The percentage of raw material required before the operation can be started.

  • The default is 0%, and this field in unavailable. LN allows you to start the operation even with no raw materials available.
Inherit Warehouse if Product is used as Phantom

Determines on which warehouse LN allocates the requirements for this component and from which warehouse it is issued if the component is a phantom.

Related topics
Job Shop Bill of Materials
Overview of use-up materials and alternative materials
Using up remaining stock of outdated items