Check Order System for Planning (tibom1220m000)

Use this session to check and optionally correct the order system of a range of items. This check prevents particular types of error in which Enterprise Planning plans only a part of the items in an item structure or fails to transfer planned production orders to the execution level because of missing operations.

Field Information

Check Effectivity against Date

the session uses the bill of material (BOM) that is valid on the date that you specify.

the session uses the current date.

Check Effectivity against Date

LN checks the item structure and the order system based on the bill of material (BOM) that is valid on this date.

Simulate Only

LN does not change the order systems of any item, but only generates a report.

Related topics
Potential errors caused by inconsistent selection of order system