Copy Request for Quotation (tdpur1201s000)

Use this session to copy an existing request for quotation (RFQ) or request for quotation (RFQ) lines, to a new or an existing RFQ. You can copy from actual or history sessions.

You can copy all lines or specific lines from a source RFQ to a target RFQ.

Note: 
  • When you copy an RFQ to an existing RFQ, the status of the target RFQ must be Created or Modified.
  • If the Copy All Lines is selected, the target RFQ receives the same structure of alternative lines as the source RFQ, only if all lines of the source RFQ are copied to a new RFQ. In all other situations, alternative lines are copied as new RFQ lines to the target RFQ.

Field Information

Source
Copy from History

you can copy an RFQ or RFQ lines from history.

RFQ

The number of the source request for quotation (RFQ).

Purchase Office

The source RFQ's purchase office.

Buyer

The source RFQ's buyer.

Target
RFQ

The number of the target request for quotation (RFQ).

Purchase Office

The target RFQ's purchase office.

Buyer

The target RFQ's buyer.

RFQ Date

The target RFQ's request for quotation date.

The current date.

Response Date

The target RFQ's response date.

Current date + number of days specified in the Default Term for Returning RFQ's field of the Request for Quotation Parameters (tdpur0100m100) session.

Copy All Lines

all lines from the source RFQ are copied.

click Select Lines... to select the request for quotation (RFQ) lines that must be copied.

Copy Bidders

all bidders from the source RFQ are copied to the target RFQ.

Copy Peg Distribution

and a source RFQ line is linked to a peg distribution, this distribution is also copied to the target RFQ line.

Project pegging in Procurement

Peg Change Reason

The change reason for manually creating the pegged supply. The reason must be specified only if the Manual Project Peg Modification check box is selected in the Project Pegging Parameters (tcpeg0100m000) session.

The project peg changes and the reason codes are logged in the Cost Peg Audit History (tpctm2500m000) session.

Note: The reason code must be of the type Project Peg Audit History and applies to all pegs in the peg distribution.

Project pegging in Procurement

Copy Additional Information

additional information from the original RFQ is copied to the target RFQ.

The additional information from the RFQ header, RFQ line, and RFQ response is copied.

Additional information fields in Procurement

Copy Texts

any text associated with the original RFQ is copied.

Note: If you copy an RFQ to a new RFQ, the text that is associated with the header and lines are copied. If you copy an RFQ to an existing RFQ, only the texts of the lines are copied.
Related topics
RFQs - additional processes