euBP Requests (lpdeu2110m000)
Use this session to create and maintain the euBP requests based on the information received from DRV (Deutsche Rentenversicherung - German Pension Insurance System). The data in this session is used for euBP audit. However, DRV can request for audits.
- This session can be accessed only if the Germany check box is selected in the Implemented Software Components (tccom0100s000) session.
- You can view the euBP audits associated with the request in the euBP Audits (lpdeu2100m000) session. This session can be accessed using the euBP Audits option from the menu.
- The data created in this session is processed using the Process euBP (lpdeu2200m000) session. This session can be accessed using the option from the menu. This option is enabled only if the Audit completed check box is cleared.
- To upload submit the euBP audit files to German Pension Insurance System (DRV), you must manually upload the exported euBP audit files to the DRV-authorized partner Xisi using the euBP-senden.de portal.
Field Information
- Audit ID
-
The identification number of the audit request. This value is specified manually.
- Audit Request
-
- Reason for Data Transmission
-
The reason for which data is transferred.
Allowed values
- 1 - Audit Notification / Audit Date
- 2 - Change of Billing Software
- 3 - Change of Service Provider
- Not Applicable
Note: By default, this field is set to 1 - Audit Notification / Audit Date. - Audit Date
-
The date when the audit must be performed.
- Delivery Date
-
The date by when the organization data must transfer the audit data to DRV electronically.
Note: This value is updated based on the value specified in the Audit Date field. This value is calculated as 11 days prior to the value in the Audit Date field (Audit Date-11). - Audit completed
-
Indicates if the euBP audit associated with the euBP request is completed.
Note: This check box is selected if the euBP audit is completed in the euBP Audits (lpdeu2100m000) session.
- Audit Periods
-
- Audit Period Start Date
-
The date when the euBP audit is initialized.
Note: Based on DRV guidelines, a request is created for 4 calendar years. However, you can modify this value. - Audit Period End Date
-
The date when the euBP audit is completed.
Note: Based on DRV guidelines, a request is created for 4 calendar years. - Transmission Period Start Date
-
The date when the data transfer to DRV for euBP audit is initialized.
Note: This value is greater than the value specified in the Audit Period Start Date field. The first date of the first fiscal period prior to the Audit Period Start Date must be specified. - Transmission Period End Date
-
The date when the data transfer to DRV for euBP audit is completed.
- Fiscal Periods
-
- Fiscal Year from
-
The fiscal year from which the euBP audit is performed.
- Fiscal Period from
-
The period of the fiscal year for which the euBP audit is performed.
- Fiscal Year to
-
The fiscal year up to which the euBP audit is performed.
- Fiscal Period to
-
The period of the fiscal year up to which the euBP audit is performed.
- Audit
-
- Created by
-
The logon code of the user who performs the euBP audit for the specified data.
- Creation Date
-
The date and time when the auBP audit is performed for the specified data.