Equipment Utilization Detail Lines (tdpur6124m100)

Use this session to record the equipment utilization associated with each bill of quantities line for an Equipment Procurement Order within a specific assessment period.

Note: 
  • This session is displayed only if the Bill of Quantities check box is selected in the Services Procurement Order Parameters (tdpur0101m000) session.
  • This session is displayed only if the Services Procurement Orders check box is selected in the Procurement Parameters (tdpur0100m000) session.
  • You can access this session by selecting Equipment Utilization Detail Lines from the References menu in the Equipment Utilization Lines (tdpur6121m100) session.
  • You can create detail lines only for the bill of quantities lines for which the value in the Cost Type field is set to Materials, Equipment, or Subcontracting
  • After a detail line is saved, the utilized values are added and updated on the corresponding equipment utilization line.

Field Information

Equipment Utilization

The equipment utilization to which the detail line is linked.

Line

The equipment utilization line number.

Sequence

The bill of quantities line sequence linked to the equipment utilization line.

Variation Line

The variation request line linked to the equipment utilization line.

Call-Off Line

The call-off line linked to the bill of quantities line.

Detail Line

Indicates the equipment utilization detail line number, linked to the bill of quantities line.

Cost Type
The cost type linked to the Bill of Quantities line.
Note: 
  • This field is displayed only if the Bill of Quantitiescheck box is selected in the Services Procurement Order Parameters (tdpur0101m000) session.
  • This field is enabled only if:
    • The value in the Sequence field is set to a value other than 0.

Allowed values

Materials
Equipment
Subcontracting
Not Applicable
Scope of Work/ Equipment/ Material
The code of the item (subcontracting, material, or equipment) that is used to identify the scope of work associated with the specific cost type linked to the selected bill of quantities line.
Note: 
  • This check box is enabled only if the value in the Line Typefield is set to Bill of Quantities.
  • • The value in this field is based on the value specified in the Cost Typefield:
    • For Materials, select an item of type Product.
    • For Equipment, select an item of type Equipment.
    • For Subcontracting, select a subcontracted service or scope of work.
Line Type
The line type linked to the Bill of Quantities line.
Note: 
  • You can set this field to Bill of Quantities only if the Bill of Quantitiescheck box is selected in theServices Procurement Order Parameters (tdpur0101m000) session.
  • You can set this field to Amount Based on Consumption only if:
    • The Bill of Quantities check box is selected in the Services Procurement Order Parameters (tdpur0101m000)session.
    • The value in the Cost Typefield is set to a value other than Not Applicable.

Allowed values

Amount Only
Rate Only
Quantity and Rate
Bill of Quantities
Amount Based on Consumption
Not Applicable
Quantity
The quantity of the item associated with the bill of quantities line.
Note: This field is enabled only if the Line Typefield is set to a value other than Bill of Quantities and Amount Based on Consumption.
Description

Specifies the type of work associated with the detail line.

Amount

The order amount associated with the selected bill of quantities line.

Note: 

The order amount is specified based on the selected line type:

  • For Amount Only lines, the amount is specified manually.
  • For Quantity and Rate lines, the amount is calculated based on the quantity and procurement rate.
  • For Rate Only lines, the order amount is defaulted from the capped amount or call-off lines.
Capped Amount

The maximum amount that is charged for the bill of quantities line, expressed in the order currency.

Note: 

If a value is specified in this field, the amount claimed using Applications for Payment or Equipment Utilizations must be less than or equal to the specified value.

Utilized Progress %

The percentage utilized for the selected detail line in the current utilization period.

Note: 

The total utilized percentage for the related bill of quantities line cannot exceed 100%.

Utilized Quantity

The quantity utilized for the selected detail line in the current utilization period.

Note: The utilized quantity specified for the detail lines is included in the total updated on the corresponding equipment utilization line.
Utilized Amount
The amount utilized for the selected detail line in the current utilization period.