Configuring project settings for major check-out
For each PLM project, you can define custom configuration settings for Major Check-Out operations. You can use these rules to manage major check-out operation separately from standard check-out processes.
Major Check-Out settings can be granularly configured across three specific tabs in the Project Configuration (pdadm3101s000) session:
- Item tab
- Document tab
- Folder tab
When the Custom settings for Major Check-Out check box is selected in the Project Configuration (pdadm3101s000) session, for a PLM project::
- Infor LN automatically identifies the Major Check-Out operation.
- The parameters from the Major Check-Out configuration tabs are applied instead of the standard check-out settings.
To enable Major Check-Out Settings:
- Access the PLM Projects (pdadm3500m000) session.
- Select Project Configuration from the References menu. The Project Configuration (pdadm3101s000) session is displayed.
- Select or open the target PLM Project.
- Select the Custom settings for Major Check-Out checkbox.
- Configure the required parameters under each tab:
- Item Tab: Define item-level checkout behavior during major revisions.
- Document Tab: Set document attachment, structure, and revision controls for major check-outs.
- Folder Tab: Configure directory and folder handling during major check-outs.
- Click Save.