Activity List for Job Shop Orders (tsspc3520m900)
Use this session to view and maintain the details of all the activities of the Job Shop Orders.
Field Information
- Group
 - 
            
The unique ID of the group.
 - Planning Sequence
 - 
            
The planning sequence of the activities for the Job Shop Orders.
 - Activity Set
 - 
            
The group planning activity number.
 - Activity Sequence
 - 
            
The sequence number of the group planning activity.
 - Activity Status
 - 
            
The status of the activity.
Allowed values
- Created
 - 
              
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
 - Planned
 - 
              
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
 - Not Planned
 - 
              
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
 - Released
 - 
              
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
 
 - Job Shop Order
 - 
            
The Job Shop Order activity number.
Note: You cannot modify this value. - Operation
 - 
            
The job shop order operation number.
Note: You cannot modify this value. - Queue Time
 - 
            
The queue time for job shop order activity.
 - Activity Duration
 - 
            
The duration of the Job Shop Orders related activity.
 - Planned Start Time
 - 
            
The start date and time for the group planning activity.
 - Planned Finish Time
 - 
            
The finish date and time for the group planning activity.
 - Earliest Start Time
 - 
            
The earliest start time of the job shop order activity.
 - Latest Finish Time
 - 
            
The latest finish time of the job shop order activity.
 - Firm Planned
 - 
            
If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.
 - Appointment
 - 
            
If this check box is selected, an appointment exists for the order activity.
 - Calendar
 - 
            
The calendar that is used to plan Job Shop Orders related activities.
 - Description
 - 
            
The description or name of the code.
 - Availability Type
 - 
            
The availability type which is used to calculate the start and finish time of the activities to be performed in each location.
 - Description
 - 
            
The description or name of the code.
 - Time Zone
 - 
            
The time zone that belongs to the specified calendar.
 - Original Group
 - 
            
The planning group number from which the activities are originating.
 - Original Activity Set
 - 
            
The planning activity set number from which the activities are originating.
 - Original Activity Line
 - 
            
The planning activity number from which the activities are originating.