Activity List for Non-Conformance Reports (tsspc3520m800)
Use this session to view and maintain the details of all the activities of Non-Conformance Reports.
Field Information
- Group
 - 
            
The unique ID of the group.
 - Planning Sequence
 - 
            
The planning sequence of the activities for the Non-Conformance Report.
 - Activity Set
 - 
            
The group planning activity number.
 - Activity Sequence
 - 
            
The sequence number of the group planning activity.
 - Activity Status
 - 
            
The status of the activity.
Allowed values
- Created
 - 
              
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
 - Planned
 - 
              
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
 - Not Planned
 - 
              
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
 - Released
 - 
              
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
 
 - Non-Conformance Report
 - 
            
The Non-Conformance Report activity number.
 - 
            
The type of the Non-Conformance Reports related activity.
Allowed values
 - Description
 - 
            
The description or name of the code.
 - Status
 - 
            
The status of the activity.
Allowed values
- Open
 - Submitted
 - Assigned
 - Dispositioned
 - Canceled
 - Closed
 
 - Activity Duration
 - 
            
The duration of the Non-Conformance Report related activity.
 - Planned Start Time
 - 
            
The start date and time for the group planning activity.
 - Planned Finish Time
 - 
            
The finish date and time for the group planning activity.
 - Firm Planned
 - 
            
If this check box is selected, the group is firm planned. That is, you cannot change the start and finish date of the group.
 - Calendar
 - 
            
The calendar that is used to plan Non-Conformance Report related activities.
 - Description
 - 
            
The description or name of the code.
 - Availability Type
 - 
            
The availability type which is used to calculate the start and finish time of the activities to be performed in each location.
 - Description
 - 
            
The description or name of the code.
 - Time Zone
 - 
            
The time zone that belongs to the specified calendar.
 - Original Group
 - 
            
The planning group number from which the activities are originating.
 - Original Activity Set
 - 
            
The planning activity set number from which the activities are originating.
 - Original Activity Line
 - 
            
The planning activity number from which the activities are originating.