Groups for Projects (PCS) (tsspc3100m700)
Use this session to view and modify group planning data for the Projects (PCS).
Field Information
- Group Set
 - 
            
The unique ID of the group set for which the attribute values are specified.
 - Group
 - 
            
The unique ID of the group.
 - Check Resources for Attribute Values
 - 
            
If this check box is selected, LN allocates resources for the Projects (PCS) based on the attribute values.
 - Check Resources for Skills
 - 
            
If this check box is selected, LN allocates resources for the Projects (PCS) based on the skills.
 - Check Resources for Availability
 - 
            
If this check box is selected, LN checks the availability of resources for the Projects (PCS).
 - Minimum Availability Percentage
 - 
            
The minimum availability percentage of the resource for the allocation.
 - Group Status
 - 
            
The least possible status of all the activities in the group.
Allowed values
- Created
 - 
              
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
 - Planned
 - 
              
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
 - Not Planned
 - 
              
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
 - Released
 - 
              
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
 
 - Maximum Activity Status
 - 
            
The highest possible status of the Projects (PCS) activity that is assigned to the group.
Allowed values
- Not Started
 - In Progress
 - Completed
 
 - Frozen
 - 
            
If this check box is selected, the group is frozen and you cannot add new groups to the existing groups.
 - Firm Planned
 - 
            
If this check box is selected, the group is firm planned and you cannot modify the start and finish date of the group.
 - Sort Method
 - 
            
The sorting method for the Projects (PCS) activities in an activity set.
Allowed values
- Earliest Start
 - Latest Finish
 - Latest Start
 - Planned Start
 - Planned Finish
 
 - Keep Sequence of Activity Sets
 - 
            
If this check box is selected, LN does not change the sequence of the activity sets when the specified group is planned.
 - Planned Start Time
 - 
            
The planned start date and time of the first activity set in the specified group.
 - Planned Finish Time
 - 
            
The planned finish date and time of the last activity set in the specified group.
 - Respect Earliest Start Time
 - 
            
If this check box is selected, LN considers the earliest start time to plan the Projects (PCS) activities.
Note:- For a project(PCS) activity, the Planned Start Time cannot be planned after the earliest start time.
 - If group is not part of a group set, the value in this field is defaulted from Respect Earliest Start Time (manufacturing) specified in the Resource Planning Parameters (tsspc0101m000) session.
 
 - Respect Latest Finish Time
 - 
            
If this check box is selected, LN considers the latest finish time to plan the j Projects (PCS) activities. The Planned Finish Time cannot be planned after the Latest Finish Time.
Note: LN re-plans the route for the activity. - Total Activity Duration
 - 
            
The cumulative duration of travel for all the activity sets in the group.
 - Time Duration Unit
 - 
            
The unit code for the total activity duration.
 - Allocated Resource
 - 
            
The resource assigned to the specified group.
 - Start Date Groups
 - 
            
The start date of the group. LN displays the details of the groups with a start date later than the specified date.
 - Finish Date Groups
 - 
            
The finish date of the group. LN displays the details of the groups with a finish date earlier than the specified date.
 - Allocated Resource
 - 
            
The code of the allocated resource based on which the group data is filtered.