Budgeted Labor Costs (tpptc3546m000)
Use this session to display the budgeted amounts and quantities with a cost-type of labor for:
- The selected project
 - The budget-cost analysis code
 
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Project Status
 - 
            
The project's status.
 - Budget Cost Analysis Version
 - 
            
The code that uniquely identifies the cost analysis.
 - Last Calculation Time
 - 
            
The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.
 - Currency
 - 
            
The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.
The following sequence is applicable:
- Project currency
 - Local currency
 - Reporting currency 1
 - Reporting currency 2
 
Note: Only the last three currencies are home currencies. - Task
 - 
            
The code that uniquely identifies the labor.
 - Reference Type
 - 
            
The nature of the labor cost object.
 - No. of Hours
 - 
            
The number of labor units for which the costs were budgeted.
 - Amount
 - 
            