Budgeted Material Costs (tpptc3545m000)
Use this session to display the budgeted amounts and quantities with a cost-type of material for:
- The selected project code
 - The budget-cost analysis code
 
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Project Status
 - 
            
The project's status.
 - Budget Cost Analysis Version
 - 
            
The code that uniquely identifies the budget-cost analysis.
 - Last Calculation Time
 - 
            
The date on which the latest budget-cost analysis was performed via the Generate Budget Cost Analysis (tpptc3200m000) session for the selected budget-cost analysis code.
 - Currency
 - 
            
The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.
The following sequence is applicable:
- Project currency
 - Local currency
 - Reporting currency 1
 - Reporting currency 2
 
Note: Only the last three currencies are home currencies. - Item
 - 
            
The code that uniquely identifies the item.
 - Quantity
 - 
            
The quantity of the material for which the material costs on the budget line were computed.
 - Unit
 - 
            
The code that uniquely identifies the unit.
 - Amount
 - 
            
The sum of the budgeted costs on the line.