Rental Resource Lines (tpptc2180m000)
           Use this session to view and maintain rental resource lines of a project, linked to a rental template. 
           
         
            Note: The header data of this session is defaulted from the Activity Budget (Equipment) (tpptc2112m000) session and cannot be modified.
           
          Field Information
- General
 - 
            
 - Project
 - The code of the project.
 - Plan
 - The code of the plan.
 - Activity
 - The code of the activity.
 - Equipment Rental
 - The code of the reference activity that is linked to the rental equipment.
 - Planned Equipment Request
 - 
            The code of the planned equipment request generated for the rental activity in a project.
            Note: This field is displayed only when the Rental Resource Lines (tpptc2180m000) session is accessed from the Planned Equipment Requests (tppss6125m000).
 - Budget Details
 - 
            
 - Quantity
 - 
            The quantity of the rental equipment.
            Note: This field is defaulted with the value of the Equipment Quantity field in the Activity Budget (Equipment) (tpptc2112m000) session.
 - Cost Amount
 - 
            The sum of the cost amounts of the rental resource lines.
            Note: If the quantity of the rental resource lines is modified, the value of cost amount in the budget is recalculated.
 - Currency
 - The currency in which the cost amount is expressed.
 - Line
 - The line number of the rental resource line.
 - Resource Type
 - 
            
The resource type of the reference activity linked to a rental template.
Allowed values
- Labor
 - 
              
The overheads are calculated for Labor cost type.
 - Overhead
 - 
              
The overheads are calculated for Overhead cost type.
 - Materials
 - 
              
The overheads are calculated for Material cost type.
 - Equipment
 - 
              
The overheads are calculated for Equipment cost type.
 - Subcontracting
 - 
              
The overheads are calculated for Subcontracting cost type.
 - Sundry Costs
 - 
              
The overheads are calculated for Sundry cost type.
 
 - Rental Product
 - 
            If this check box is selected, you can specify a rental product for the rental resource line.
            Note: This check box is enabled only if the Resource Type field is set to Equipment.
 - Resource Item
 - 
            The rental product specified for the rental resource line.
            Note: This field is enabled, if:
- The Resource Type field is set to Materials.
 - The Resource Type field is set to Equipment and the Rental Product check box is selected.
 
 - Description
 - Resource Cost Object
 - 
            The cost object specified for the rental resource line. This value is based on the resource type.
            Note: This field is enabled if the Resource Type field is set to Labor, Equipment, and Sundry Costs.
 - Per Unit Quantity
 - The quantity required for one unit of rental equipment.
 - Total Quantity
 - 
            The total quantity of the resource item or cost object.
            
Total Quantity = Per Unit Quantity x Equipment QuantityNote: The equipment line quantity of the equipment budget line or estimate line or planned equipment request from where the rental resource lines session is accessed is considered as Equipment Quantity. - Quantity Unit
 - 
            The unit in which the quantity is expressed. 
            Note: This field must be specified if the Resource Type is set to:
- Material
 - Equipment
 
 - Amount of Time
 - 
            The duration for which the resource is used.
            Note: The value in this field is defaulted from the Activity Budget (Equipment) (tpptc2112m000) session.
 - Time Unit
 - 
            The unit in which the time is expressed.
            Note: This field must be specified if the Resource Type is set to:
- Labor
 - Equipment
 
 - Cost Rate
 - The cost per unit for the cost object.
 - Cost Amount
 - The total cost amount for the rental resource line.
 - Currency
 - The currency in which the cost amount is expressed.
 - Cost Component
 - The cost component at which the cost control is implemented.
 - Description