Rescheduling Messages for Equipment (tppss6106s000)
Use this session to view the details of a rescheduling message for an equipment purchase order generated during the last PRP run.
Rescheduling messages are generated for PRP orders of the following types:
- Firm-planned
 - Confirmed
 - Transferred
 
Rescheduling messages are not generated for transferred purchase budget lines.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Order Type
 - 
            
The order type to which the rescheduling message applies.
This field can have the following values:
- PRP Purchase Order for the Firm-planned or Approved status
 - Purchase Order for transferred PRP purchase orders
 - Request for Quotation for transferred PRP purchase orders
 - PRP Warehouse Order for the Firm-planned or Approved status
 - Warehouse Transfer for transferred PRP warehouse orders
 
 - Order Number
 - 
            
The code of the order to which this message applies.
 - Position Number
 - 
            
The position number of the order line. As an order can have multiple order lines, this number is used to identify the particular line to which the rescheduling message applies.
 - Sequence Number
 - 
            
No Help topic is associated with this item.
 - Sequence Number
 - 
            
The sequence number which identifies the rescheduling message.
 - Equipment
 - 
            
The code that uniquely identifies the ordered equipment.
 - Reference Type
 - 
            
Indicates if the equipment is standard or project specific.
 - Transaction Date
 - 
            
The date and time when the rescheduling message was generated.
 - Cost Determination
 - 
            
Indicates how cost amounts relating to this cost object are calculated in the actual budget.
Allowed values
- Quantity
 - 
              
The costs related to the subcontracting cost object are calculated, by quantity-based measure of productivity.
 - Amount of Time
 - 
              
The costs related to the subcontracting cost object are calculated, by time-based measure of productivity. Example, the subcontractor can be paid by the hour.
 - Rate Only
 - 
              
The costs related to the subcontracting cost object are calculated, based on only an agreed rate.
 - Amount Only
 - 
              
The costs related to the subcontracting cost object are calculated, based on only an amount (lump sum).
 
Note: The field can be set to Rate Only or Amount Only only if:- The Services Procurement is set to In Preparation or Active in the Implemented Software Components (tccom0100s000) session.
 - The Procurement by field is set to Subcontracting Procurement Order.
 
 - Amount of Time
 - 
            
The required quantity based on the project control budget.
 - Amount of Time
 - 
            
The ordered quantity.
 - Delivery Date
 - 
            
The required delivery date of the equipment. This date is calculated from the project control budget data.
 - Delivery Date
 - 
            
The planned delivery date of the ordered equipment.
 - Message
 - 
            
The type of rescheduling message.