Performance Measurement Generate Codes (tpppc5500s000)

Use this session to maintain the used baseline and version per generate code.

Field Information

Project

The project code.

Generate Code

The generate code.

Baseline

The performance measurement baseline code.

Version

The version number.

Date to

The date up to which the performance measurement is generated.

Planned Value

The date for which performance measurement of scheduled work is generated.

Earned Value

The date for which performance measurement of performed work is generated.

Actual Cost

The date for which performance measurement of actual work is generated.

Budget at Completion

The date for which performance measurement of BAC work is generated.

Estimate at Completion

The date for which performance measurement of EAC work is generated.

Budget Type
The budget type for which performance measurement generate code is defined.
Note: By default, this field is set to Top Down.

Allowed values

Top Down

Calculating the cost or sales amount in a top down structure means you distribute a top amount to the lower level elements. There is no aggregation of the costs. The structural element you work from determines the amount. The rule is that LN looks for amounts on estimate lines on level Total/Cost Type/Other Structure/Detail and in that order.

Bottom Up

Calculating the cost or sales amount in a bottom up structure means you give exact amounts for lowest level elements and aggregate them to make the top amount.

Budget Cost Analysis Version
The budget cost analysis version for which performance measurement generate code is defined.